Case Study: AEP – Baileysville-Bolt 138kV Line Rebuild – Access Road 50

Access Road 50 Land Subsidence Repair

  • Customer: EPC Services Company | AEP Transmission

  • Location: Sabine, WV

  • Date: 9/2021

  • Temporarily stabilize slide area and install environmental BMPs and SWPPP controls. Excavate to bedrock grade and construct battered bonding bench. Install 247 Gabion rock filled mesh baskets of various sizes to form retention wall. Reconstruct suitable access road and permanently stabilize jobsite.