Strip field and mow access edges, install environmental BMPs, install access road base aggregate and cap aggregate, install geotextile separation fabric and grade aggregate on yard. Cap yard with aggregate, install highway signs, and install gate. Provide waterline and service to office buildings and finalize jobsite. Total aggregate placed was approx. 18,900 tons.